Brick Masonry

Brick Masonry

  • 1. Introduction
  • 2. Manufacturing
  • 3. Standards and codes
  • 4. Brick types
  • 5. Properties and tests (IS 3495)
  • 6. Design and detailing
  • 7. Common failures and remedies
  • 8. QA and QC checklist
  • 9. Brick bonds
  • 10. Sample specification clause
  • 11. BOQ lines
  • 12. Method statement — brickwork
  • Disclaimer
🧭

Purpose: consultant-ready guide to brick masonry. Use the TOC to jump to manufacturing, standards, properties and tests, design and detailing, failures, QA, bonds, spec, BOQ, and method statement.

1. Introduction

Burnt clay brick masonry is a ubiquitous walling system for load-bearing and infill walls. When executed correctly it provides structural performance, durability, fire resistance, and reasonable thermal mass.

2. Manufacturing

  • Soil selection and testing: Sand:silt:clay balance. Organic matter < 1%. Control plasticity. Remove inert contaminants.
  • Preparation and pugging: Uniform moisture content. Pug mill for consistent plasticity.
  • Moulding: Hand-moulded or extrusion (wire-cut preferred for precision).
  • Drying: Controlled 7–14 days in shade and ventilation. Avoid rapid drying.
  • Burning: Clamp or Hoffman kiln at 900–1100°C to achieve vitrification without overfiring.
  • Cooling and grading: Sort by color, sound (ring test), and size tolerance. Store dry on pallets.

3. Standards and codes

  • IS 1077 — Common burnt clay building bricks.
  • IS 3495 (Parts 1–3) — Testing bricks (compressive, absorption, efflorescence).
  • IS 2212 — Code of practice for brickwork.
  • IS 2250 — Masonry mortars.
  • IS 1905 — Structural masonry design.

4. Brick types

Type
Description
Application
First class bricks
Uniformly burnt, sharp edges, water absorption < 15%
Structural walls
Second class bricks
Slightly over/under burnt, minor imperfections
Internal walls, plastered surfaces
Fly ash bricks
Fly ash and lime
Sustainable, uniform finish
Fire bricks
High alumina content
Kilns and chimneys

5. Properties and tests (IS 3495)

Parameter
Test standard
Typical acceptance
Compressive strength
IS 3495 Part 1
≥ 7.5 MPa typical for first class (specify project grade)
Water absorption
IS 3495 Part 2
< 20% (first class)
Efflorescence
IS 3495 Part 3
Nil to slight
Dimensional tolerance
IS 1077
± 3 mm (L/W/H)
Soundness
Ring test
Clear ring indicates acceptable
Bulk density
—
≈ 1800–1950 kg/m³

6. Design and detailing

  • Wall thickness: 115, 230, 290 mm as per structural design.
  • Joints: 10 mm nominal mortar joints; maintain consistency.
  • Control joints: Provide every 6 m horizontally, near openings, corners, and material junctions. Width 10–12 mm with suitable sealant.
  • DPC: Minimum 150 mm above external ground level; continuous at plinths.
  • RCC integration: Use galvanized bonding mesh and starter bars or shear keys at junctions. Provide lintel and sill bands.
  • Curing: Mist spray for a minimum of 7 days.

7. Common failures and remedies

Symptom
Likely causes
Diagnostic check
Remedial step
Efflorescence
Soluble salts or rising damp
Salt test, moisture mapping
Remove salts, apply breathable repellent, fix DPC/drainage
Rising damp at plinth
Missing/failed DPC
Moisture probe, visual staining
Retrofit DPC and improve drainage
Vertical or horizontal cracks
Settlement, lack of movement joints, thermal movement
Crack mapping, tell-tales
Provide/enlarge joints, stitch as needed, underpin if structural
Bulging walls
Poor bonding, inadequate support, moisture
Visual deflection
Rebuild section, install ties, improve mortar strength
Hollow sounds under plaster
Poor key or weak suction control
Hammer sounding
Remove and re-plaster with bonding slurry and PMM

8. QA and QC checklist

  • MTCs for bricks, sand, and cement.
  • Sand sieve analysis within Zone II (IS 383).
  • Brick compressive strength test per batch.
  • Mortar mix verification (1:6 or as specified) by weight.
  • Joint thickness checks: 5 readings per 50 m²; mean 10 mm ± 2 mm.
  • Wall plumb: ± 3 mm per 2 m.
  • Curing log: start time, method, minimum 7 days.
  • Pond test for wet areas: 72 hours without leakage.

9. Brick bonds

  • English bond
  • Flemish bond
  • Rat-trap bond (hollow cavity improves thermal performance)

10. Sample specification clause

Supply and construct 230 mm thick brick masonry using first class burnt clay bricks in cement mortar 1:6 (1 cement : 6 washed sand), including scaffolding, raking of joints, DPC installation, lintels, and curing for 7 days. Comply with IS 1077, IS 2212, and IS 2250. Rate to include materials, labour, wastage, curing, and testing as per ITP.

11. BOQ lines

  • Brick masonry 230 mm in CM 1:6 — unit m³
  • Brick masonry 115 mm partition in CM 1:4 — unit m²
  • DPC with bituminous felt 2 mm — unit m
  • External cement plaster 20 mm (2 coats) — unit m²
  • Flush pointing with polymer-modified mortar — unit m

12. Method statement — brickwork

  1. Scope and references: IS 1077, IS 2212, IS 2250.
  2. Materials and acceptance: MTCs, sample tests, sand FM and silt checks, cement checks, mortar 1:6 by weight.
  3. Execution: Layout and levels; plumb profiles every 3 m; full-bed laying; 10 mm joints; reinforcement as detailed; DPC; lintels and bearings.
  4. Finishing and curing: Rake joints; protect from weather; cure 7 days; QA checks.
  5. Handover and tests: Dossier with MTCs, test reports, photos, curing record, ponding test results.

Disclaimer

SpecX is a neutral, brand-agnostic resource based on standards and best practices. Cross-check with project requirements and local codes before finalizing specifications.